Toyota’s North Carolina battery factory entered the vehicle supply chain in 2025 through hybrid vehicles. By the company’s November opening announcement, it was shipping hybrid battery modules to Toyota Kentucky and Mazda Toyota Manufacturing in Alabama, even as other parts of the enormous site continued their ramp toward production.
The year’s sequence began with a February 5 announcement that the plant was ready to start making batteries. Toyota then expected shipments in April. Its subsequent facility history records the start of shipments in June. Those dates capture a plan and a reported result; the cited records do not explain the difference.
That distinction is useful for a project whose “opening” encompassed several separate activities. Equipment can be installed, trialed and qualified before a line supplies vehicle assembly plants. A ceremony can celebrate the broader operation while additional buildings and product lines remain at different stages.
Toyota established the battery company in November 2021. Its February 2025 account described ownership as 90% Toyota Motor North America and 10% Toyota Tsusho. The facility was the automaker’s first in-house battery plant outside Japan and its eleventh manufacturing plant in the United States. The February staffing figure—approximately 5,000—was explicitly planned employment.
One site, different production stages
Toyota designed the operation to serve three kinds of vehicles: conventional hybrids, plug-in hybrids and battery-electric models. The shorthand “EV battery factory” can obscure that range and the order in which production develops.
The facility’s 2025 summary records hybrid battery production beginning during the year. It separately lists completed building construction for battery-electric and plug-in-hybrid operations, equipment trials for the former, and equipment installation for the latter. These milestones are substantial, but they describe different distances from repeat deliveries.
The November 12 announcement put the site investment at $13.9 billion and described a planned 14-line operation capable of producing 30 gigawatt-hours annually at full capacity. Additional lines were scheduled to launch through 2030. The capacity figure therefore described the completed operation’s intended scale, rather than batteries already produced during 2025.
Gigawatt-hours measure the energy capacity of the batteries manufactured. They do not directly specify how many vehicles a plant can supply: that depends on the size of the batteries and the mixture of vehicle programs. The three propulsion categories make that distinction particularly relevant here.
For the vehicle factories already receiving modules, North Carolina represented a new domestic source within Toyota’s production network. For the battery factory itself, consistent shipments were a more immediate operating measure than its eventual headline capacity.
The November event also brought an announced commitment of up to $10 billion in additional U.S. investment over five years. That was a separate companywide commitment, not another $10 billion already spent on the North Carolina battery site.
The tangible 2025 result was a functioning hybrid-battery supply route, alongside preparation for a broader product mix. Tracking the remaining lines individually—through installation, trials and regular shipments—will show how much of the planned manufacturing platform becomes available to Toyota’s assembly plants.
Sources
- Toyota Powers On New North Carolina Automotive Battery Plant — Toyota Motor Corporation · 2025-02-05.
- Toyota Battery Manufacturing North Carolina — Toyota USA Newsroom.
- Toyota Charges into U.S. Battery Manufacturing — Toyota Motor North America / PR Newswire · 2025-11-12.